Visa is looking for a few good people to run its next-generation data centers.
In July, the electronic payments company posted a job listing on the Data Center Job Board for a senior facilities engineer in Virginia to ensure the smooth operation and launch of new state-of-the-art data centers.
Visa is looking to mimic the 2006 launch of its Operations Center Central (OCC) processing facility in Denver in other data centers around the globe. Visa is pushing the envelope of virtualization in that facility and two others in different locations.
"OCC is an ongoing project," says Andy Lewis, Visa's head of global engineering at the Denver OCC. "Just as we complete one aspect of it there's going to be something else that comes along that is a further enabler to reduce costs and increase reliability and availability, while managing risk at the same time. Is there ever an end state?"
Its business would say no. Visa's 1.6 billion global card-holders account for more than US$3 trillion in annual transaction volume, which is growing at a 20 percent per-year clip. VisaNet, the company's global network, serves as the backbone for roughly one-seventh of American consumer expenditure.
Each OCC data center will handle more than US$1 trillion in annual transaction volume and according to Visa was designed to meet the growing volume of electronic credit, debit and prepaid transactions for the foreseeable future. Network, server and storage virtualization are key to enabling that.
The OCCs run a single synchronized image of transaction processing around the globe. And each OCC runs multiple instances -- or virtual images -- of that single image within the data center. This gives Visa "redundancy within redundancy" for credit or debit authorization, and the ability to failover to another data center as well as internally within a data center: Visa engineers at an OCC can manage another data center thousands of miles away connected over the company's VisaNet global payments network.
Virtualization has also helped Visa manage costs. By allocating or replicating processing cycles logically, Visa's IT budget went up only 3 or 4 percent, and unit costs were cut by about 50 percent between 2000 and 2007, as transactions grew at that 20 percent annual clip, CIO Michael Dreyer said at Cisco conference last summer.
Latest on Data Centres
- Half of data centers surveyed plan 2009 cutbacks
- VMware wants a bigger role in your data center
- Cisco planning significant data center assault
- Alcatel-Lucent cuts jobs, focuses attention on three sectors
- Elastic IT resources transform data centers
- Gartner's Top 10 disruptive data-center technologies
- Microsoft wants a Ford Model T data center
- Transmitting data from the middle of nowhere
- Scotland hotbed for green data centres
- HR group builds virtual DR with VMware
IT Services Essentials
- Gartner: Top 30 offshore locations for 2008
- HP integrates EDS into technology operations
- IBM Q3 revenue rises, but signs of downturn loom
- HP chief Hurd fields questions about EDS buy
- IBM to open services centre in Ballarat
- The 5 quickest returns on your green investment
- HP buys EDS for US$13.9 billion
- Fujitsu taps hydrogen power to fuel energy savings
- Data center mushrooming? Why not get rid of it?
TechWorld Jobs (beta)
Whitepapers
- Enterprise Wireless WLAN Security
- Email Archiving Implementation: Five Costly Mistakes to Avoid
- Discover the advantages of an open architecture multi-vendor network solution
- Solve Exchange Storage Problems Once and For All: A New Approach without Stubs or Links
- Understanding Email Marketing: A Guide for SMBs
TechWorld Blogs
-

TalkingTech
The view from the top of IT with TechWorld Editor Rodney Gedda
-

Entrenched
Cooking up better code, IDG's developers reveal some of their secrets
-

Broadband Voice
Darren Pauli digs in from the front line of Australia's broadband battleground
Recent blog posts
- Telstra kicked out of NBN process
- Linux on the iPhone won’t change the world - yet
- A Novell approach to business
- An open storage stack? I like the sound of that
- The mobile clone wars: fighting for a better phone experience
- Stopping the "Clean Feed"
- Identifying web platforms
- Clean Feed ‘not technically possible’
- No Clean Feed - well duh!
- Conroy's content cops still on the cards
Recent comments
- Hahahahhahahahhahahaha!
12 min 14 sec ago - BUY HTC TOUCH MAX 4G AT $260USD, TOUCH G1 AT $250USD,TOUCH HD
2 days 10 min ago - GrIDsure & Mike Bond's 'old' criticism
3 days 2 hours ago - Ah, the joys of being a digital nomad!
4 days 8 hours ago - Thanks
4 days 10 hours ago - re hope cottage
4 days 16 hours ago - Best CRM I have found
1 week 2 days ago - milbarn
1 week 6 days ago - milbarn
1 week 6 days ago - Compare Usenet Providers
2 weeks 6 hours ago - BUY Nokia N85 AT $240USD, HTC TOUCH PRO AT $230USD, APPLE IPHON
2 weeks 5 days ago - BUY APPLE IPHONE 3G SERIES AT $220USD, 8GB GOLD AT $200USD
2 weeks 5 days ago - BUY HTC TOUCH 3G AT $260USD, TOUCH G1 AT $250USD,TOUCH HD AT $
2 weeks 5 days ago - BUY BLACKBERRY STORM 9500 AT $260USD,BLACKBERRY BOLD 9000 AT $
2 weeks 5 days ago - Re:
2 weeks 6 days ago - Lto-4 Tape
4 weeks 6 days ago - Clarifaction of article
6 weeks 1 day ago - COBOL - Safe Bet
6 weeks 1 day ago - The most effective recycling method is to reuse!
6 weeks 1 day ago - Reduce, Reuse and Recycle!
6 weeks 1 day ago